Mississippi’s Environmental Quality Permit Board has doubled down on a controversial permit issued to SpaceX earlier this year, clearing the way for its artificial intelligence division to bring dozens of permanent turbines to Southaven, Mississippi.

At the close of a Nov. 9-10 evidentiary hearing in Jackson, the board elected to uphold the permit, which would allow SpaceX subsidiary MZX Tech to install 41 stationary gas turbines at its Southaven energy plant. Members voted 6-1 in favor of retaining the permit without changes, with Board Chairman and Mississippi Department of Agriculture and Commerce Commissioner Andy Gipson the lone dissenter.

A coalition of local groups had appealed the permit’s approval, claiming certain elements violate state and federal regulations. Challengers included the Safe and Sound Coalition in Southaven, Young, Gifted and Green in Memphis, Tennessee, and the Mississippi chapter of the NAACP.

“The board took its obligations very seriously in weighing the evidence in this matter,” Kim Turner, a Mississippi assistant attorney general who presided over the hearing, said in announcing the board’s verdict. “But the evidence, unfortunately, was insufficient to prove these bases for the appeal.”

The two-day hearing resembled a formal court proceeding, with attorneys for the appellants and MZX Tech offering evidence and witness testimony to support their claims. The Mississippi Department of Environmental Quality also defended its preparation of the permit to the board, which is made up of representatives from other state agencies.

The outcome of the hearing was a blow for Safe and Sound Coalition Executive Director Shannon Samsa, who described it as the latest failure by state authorities tasked with protecting public safety.

“It feels like we are screaming into a void,” Samsa told reporters following the permit board’s decision. “There’s no one listening to us.”

How We Got Here

SpaceX’s Southaven plant powers its Colossus 2 data center in neighboring Memphis, which in turn powers Grok, the company’s controversial AI chatbot. Since August 2025, Mississippi regulators have allowed the plant to operate a growing number of gas turbines without permits, sparking widespread backlash and complaints about noise and air pollution. SpaceX absorbed xAI and affiliate MZX Tech earlier this year, and the unit rebranded to SpaceXSI in October.

In March, the permit board approved the installation of 41 permanent turbines at the Southaven complex, allowing SpaceX to construct one of the largest power plants in Mississippi. The new machines would replace the unpermitted turbines currently housed at the site, which emit an array of air pollutants linked to various chronic illnesses.

Following the permit’s authorization, local organizations filed an appeal, setting the stage for last week’s evidentiary hearing. The groups argued that SpaceX and MDEQ made crucial errors while crafting the permit, resulting in a document that violates state and federal laws and doesn’t sufficiently protect public health.

Core Arguments

Much of the challengers’ concerns with the permit centered on the absence of so-called emissions offsets—a process designed to prevent excess fumes in pollution-heavy regions like metro Memphis. While Mississippi law mandates these offsets in areas with active air quality violations, MDEQ failed to include them in the permit—even though pollution levels around Southaven exceeded regulatory standards at the time of its approval, the groups alleged in their appeal.

“Mississippi law required MDEQ to implement emissions offsets to mitigate the impact from (SpaceX’s plant), but they did not,” said Patrick Anderson, a senior attorney at the Southern Environmental Law Center, which represented the appellants at the evidentiary hearing. “I have worked with DEQ and I have high opinions of their work in many instances, but in this case, they got things wrong.”

A row of large turbines with the sun setting behind them, powerlines fuzzy in the haze of the heat from the turbines
Gas turbines are seen at the xAI facility, Monday, Dec. 15, 2025, in Memphis, Tenn. Turbines in Memphis and in nearby Southaven, Miss., power a set of xAI data center facilities in the area. AP Photo/George Walker IV, File

Beyond the permit’s lack of offsets, MDEQ and SpaceX left out several nearby sources of pollution when evaluating the plant’s cumulative impacts in the area—an omission that made it easier to demonstrate the project would not contribute to ambient air quality violations, SELC attorneys argued. They also objected to several of the turbine models earmarked for the site, claiming federal law required SpaceX to consider less polluting alternatives.

“The problem revolves around the eight largest turbines in the permit, which happen to be refurbished aircraft engines,” Anderson said. “(SpaceX) failed to even consider cleaner turbines, or that they could use more efficient pollution controls to make these turbines as clean as (other models).”

SpaceX’s attorneys countered that their client followed all applicable rules and protocols while preparing the permit for consideration. The company worked closely with MDEQ throughout the application and drafting process, attorneys explained, and decisions around pollution modeling and emissions controls were made with input from the Environmental Protection Agency.

“The petitioners may not like this project,” Trudy Fisher, an attorney for SpaceX who served as MDEQ’s executive director from 2007 to 2014, told the permit board. “But not liking a project is not a reason to set aside a permit that meets every requirement of state law, regulations, and the Clean Air Act.”

While Fisher framed the EPA’s involvement in the drafting process as proof of the permit’s validity, Anderson stressed that the agency relies on external reviewers to ensure its work is error-free.

“EPA has always required public notice and comment” on permits like the one issued to SpaceX, Anderson concluded. Even if the agency signed off on some components of the permit, “that does not mean that everybody got it right.”

What Comes Next

Last week’s regulatory hearing is part of a larger battle over SpaceX’s operations along the Mississippi-Tennessee border. In October, a federal judge ruled that the NAACP can move forward with a lawsuit accusing the company of Clean Air Act violations, denying a motion from SpaceX to dismiss the case. A separate class-action suit from Southaven residents is also pending in federal court.

These lawsuits offer another opportunity to hold SpaceX accountable following the permit board’s decision, organizations challenging the permit told the Mississippi Free Press. Upcoming elections, meanwhile, could serve as a referendum on officials who’ve failed to shield residents from the company’s harms, the head of one of those groups emphasized.

“As a public servant, you should be listening to your constituents,” Latricea Adams, the founder and CEO of Young, Gifted and Green, told reporters after the hearing. “These people who are in these seats, they’re not safe.”

Andy Gipson stands behind a podium and speaks into a microphone at the Neshoba County Fair
Mississippi Agriculture Commissioner Andy Gipson, pictured at the Neshoba County Fair on July 25, 2025, was the only member of the Mississippi Environmental Quality Permit Board to vote against SpaceX’s permit allowing one of its subsidiaries to install 41 permanent gas turbines in Southaven, Miss. MFP Photo by Heather Harrison

In explaining his vote against the permit, Agriculture Commissioner Andy Gipson said he did not get adequate answers to his questions about the Southaven plant’s potential impacts. Gipson, a Republican candidate in Mississippi’s 2027 gubernatorial race, released a memo in July calling on data center operators to disclose certain financial and environmental information prior to receiving permits.

“I think the answer that is necessary for this whole industry to succeed is going to be honesty and transparency,” Gipson told reporters, adding that he will be asking the same questions of all data center projects moving forward. “People are skeptical of what’s happening. They can’t get answers, and we just simply need to get the truth.”

Appellant groups could still appeal the permit board’s decision in court. As of Nov. 10, however, SELC attorneys said they were still weighing their options.

Follow the Mississippi Free Press’ coverage of data centers and read past stories here.

Mississippi Free Press stories are always free because we believe everyone should have access to quality journalism. Donations from readers like you make that possible. Please click here to give to help sustain and grow vital, people-over-power journalism for Mississippians.

Readers can sign up for our free newsletters here.

Environmental Reporter Illan Ireland is Mississippi Free Press’s bilingual environmental reporter in partnership with Report for America. Prior to joining the Mississippi Free Press, he completed a fellowship with The Futuro Media Group in New York City, taking on projects related to public health, climate change and housing insecurity. His freelance work has appeared in City Limits and various Futuro Media properties. Illan holds a B.A. from Wesleyan University and an M.S. from the Columbia Journalism School, where he spent a year covering the drug overdose crisis unfolding in New York City. He’s a Chicago native, a proud Mexican American and a lover of movies, soccer and unreasonably spicy foods. You can reach him at illan@mississippifreepress.org.